NEW QUESTION 1

Using the following data, what is the Schedule Performance Index (SPI)? EV= $500 PV= $750 AC= $1000 BAC= $1200

  • A. 0.67
  • B. 1.5
  • C. 0.75
  • D. 0.5

Answer: A

NEW QUESTION 2

Inputs to the Plan Schedule Management process include:

  • A. Organizational process assets and the project charter,
  • B. Enterprise environmental factors and schedule tools.
  • C. Time tables and Pareto diagrams.
  • D. Activity attributes and resource calendars.

Answer: A

NEW QUESTION 3

What type of project structure is a hierarchically organized depiction of the resources by type?

  • A. Organizational breakdown structure (OBS)
  • B. Resource breakdown structure (RBS)
  • C. Work breakdown structure (WBS)
  • D. Project breakdown structure (PBS)

Answer: B

NEW QUESTION 4

Which of the following is a group decision-making technique?

  • A. Brainstorming
  • B. Focus groups
  • C. Affinity diagram
  • D. Plurality

Answer: D

NEW QUESTION 5

An input to the Estimate Activity Resources process is:

  • A. Activity resource requirements.
  • B. Published estimating data.
  • C. Resource calendars.
  • D. Resource breakdown structure (RBS).

Answer: C

NEW QUESTION 6

A reward can only be effective if it is:

  • A. Given immediately after the project is completed.
  • B. Something that is tangible.
  • C. Formally given during project performance appraisals.
  • D. Satisfying a need valued by the individual.

Answer: D

NEW QUESTION 7

Typical outcomes of a project include:

  • A. Products, services, and improvements.
  • B. Products, programs, and services.
  • C. Improvements, portfolios, and services.
  • D. Improvements, processes, and products.

Answer: A

NEW QUESTION 8

Which of the following is a tool and technique used in all processes within Project Integration Management?

  • A. Records management system
  • B. Expert judgment
  • C. Project management software
  • D. Issue log

Answer: B

NEW QUESTION 9

In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?

  • A. Performing
  • B. Storming
  • C. Norming
  • D. Forming

Answer: C

NEW QUESTION 10

A tool and technique used in the Develop Project Charter process is:

  • A. change control tools
  • B. expert judgment
  • C. meetings
  • D. analytical techniques

Answer: B

NEW QUESTION 11

Labor, materials, equipment, and supplies are examples of:

  • A. Resource attributes.
  • B. Resource types.
  • C. Resource categories.
  • D. Resource breakdown structures (RBS).

Answer: C

NEW QUESTION 12

The chart below is an example of a:
PMP dumps exhibit

  • A. Responsibility assignment matrix (RAM)
  • B. Work breakdown structure (WBS)
  • C. RACI chart
  • D. Requirements traceability matrix

Answer: D

NEW QUESTION 13

Which of the following is an example of a risk symptom?

  • A. Failure to meet intermediate milestones
  • B. Force of nature, such as a flood
  • C. Risk threshold target
  • D. Crashing, front loading, or fast tracking

Answer: A

NEW QUESTION 14

Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?

  • A. Identify Risks
  • B. Plan Risk Management
  • C. Perform Qualitative Risk Analysis
  • D. Perform Quantitative Risk Analysis

Answer: C

NEW QUESTION 15

Which of the following tools or techniques is used for Estimate Activity Duration?

  • A. Critical path
  • B. Rolling Wave
  • C. PDM
  • D. Para metric

Answer: D

NEW QUESTION 16

Which of the following is an output of Close Procurements?

  • A. Accepted deliverables
  • B. Organizational process assets updates
  • C. Managing stakeholder expectations
  • D. Performance reports

Answer: B

NEW QUESTION 17

The process of estimating the type and quantity of material, human resources, equipment, or supplies required to perform each activity is known as:

  • A. Collect Requirements.
  • B. Conduct Procurements.
  • C. Estimate Activity Durations.
  • D. Estimate Activity Resources.

Answer: D

NEW QUESTION 18

A project manager should document the escalation path for unresolved project risks in the:

  • A. Change control plan
  • B. Stakeholder register
  • C. Risk log
  • D. Communications management plan

Answer: D

NEW QUESTION 19

The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:

  • A. Responses
  • B. Appetite
  • C. Tolerance
  • D. Attitude

Answer: A

NEW QUESTION 20

An input to the Perform Quantitative Risk Analysis process is the:

  • A. quality management plan.
  • B. project management plan.
  • C. communications management plan.
  • D. schedule management plan.

Answer: D